Junhua Internal Training: A Brief Discussion on U9 Production Orders
2. During the manufacturing process, products undergo different tasks and undergo more than one processing step. For these different processing steps, we do not need to place a separate production order for each step. Instead, we can regard these steps as a process route of a production order.
There is no need to divide production orders too finely, otherwise too much energy will be spent on compiling material files, material lists, process routes and records required for production control, but no obvious improvement in efficiency will be achieved.
Semi-finished product production order: Applicable to homemade products such as ordinary granulation, extrusion, molding, etc., which must have a bill of materials but no process route;
R&D semi-finished product production order: Applicable to the R&D of homemade products such as granulation, extrusion, and molding. There must be a bill of materials but no process route.
Manual production order : Applicable to the situation of no source documents, such as inventory orders, R&D orders without source, etc., and the production order is filled out manually.
Approved: The status of a document that has been saved, submitted, reviewed, but not started;
Start work: save, submit, review, and start work but not complete the document status;
Completion: The status of a document that has been saved, submitted, reviewed, started and completed.
Production orders with status “Start”.
In the production order process, if the process feedback has been done, it cannot be changed, but if the process feedback has not been done, it can be changed;
In the production order output, you can only add new output, and cannot modify the existing output information;
Production order notes can be modified.